Tuesday 10 March 2015

BIM: A two-way flow of information


There are a lot of interesting discussions happening at the moment around BIM as the industry moves towards reaching BIM Level 2 maturity before April 2016. Our first #BIM4M2chat with Steve Thompson, chair of BIM4M2, on 3rd February 2015 raised many great questions and comments from the product manufacturing community about how they are adopting BIM.
Why can’t BIM inform a supplier when their products have been specified?
A small manufacturing company approached me with their concern that, as a supplier, they rarely get to know when their products have been specified until the traditional old way of either receiving requests for tender information from contractors or sub-contractors, or following up on projects.
With BIM being promoted as a process that can improve efficiencies within the supply chain, I wanted to look at why this might be happening, and spoke to Steve in more detail about this issue.
The industry is focusing on working with product manufacturers to adopt BIM processes in time for April 2016, including providing the right information and delivering this content in the right way. It seems that looking at how we can improve efficiencies in the supply chain – including establishing a two-way flow of information – is the next stage.
Early manufacturer engagement
It makes sense that manufacturers want to know at an early stage what projects their products have been specified on so they can offer expert advice from the beginning, as well as looking to reduce the impact of lead times for a particular product, enabling them to schedule production and helping to improve internal processes.
We often talk about early contractor engagement, but is there also a need to focus on early manufacturer engagement to ensure the supply chain is receiving the right information at the right time?
Steve agreed that this is a real problem for product manufacturers. He said: “My concern is that engagement with manufacturers is too often seen as a one-way, not a two-way process. It is a real missed opportunity to make significant efficiencies through the supply chain.”
“There are short term solutions. In creating content we need to make sure manufacturers and the supply chain and specifiers work together, instead of throwing information over the fence and saying that we ‘do BIM’. We need to maintain the link between the manufacturing process and project (and product) delivery and operation."
Steve explains that often the best way to do this is for a product manufacturer to hold content on their own website, or issue it on request, so they know when their content is being used. Specifiers can also contact manufacturers directly from the model, which improves the speed of information transfer and ensures additional support can be given where required.